DEMOLITION
Illustrated
(left) is W F Doyle's Liebherr R954V Extra-Long Reach Demolition machine
capable of 25 metres working height fitted with Allied Labounty Universal
Processor and dust suppression equipment. This allows just the one machine
to undertake a total demolition task with ease and in safety, using
the universal processor to demolish a structure with precision handling
and in a controlled manner.
The Universal Processor has interchangeable jaws consisting of steel,
concrete cracking, concrete pulverising and tank / plate jaws. |
WOOLFALL
HEIGHTS
Two
fifteen storey blocks 41 metres high situated on a busy through road
and bus route in a residential and shopping area.
|
|
RANDLE HEIGHTS
Two
eighteen storey blocks situated in a residential area on a busy public
transport route.
|
|
|
This
contract involved the removal of one hundred and sixty eight flats built
in 1960. They were situated in a twenty two-storey block, 63 metres
high, at Upper Parliament Street, Liverpool. The construction was in-situ
reinforced concrete, all of which had to be reduced to the ground and
the site graded and levelled. Throughout the demolition work there were
occupied dwellings close to the building, on one side they were three
metres away, on the other side they were ten metres away. To avoid damage
to the dwellings the sidewalls of the building were sheeted from top
to bottom before work began. The whole of the structure was covered
by scaffolding and as each storey was taken down the work platforms
at that level were enclosed by fragmentation sheeting to contain loose
rubble as the area was dismantled. From the erection of hoarding around
the site to the final clearance of the ground the contract was finished
within the specified period, with no disturbance to the tenants, in
the houses on either side of the block. |

|
Two
eleven storey high rise blocks of maisonettes and flats, 30 metres high.
Constructed of no-fines exterior and interior walls, reinforced concrete
gables and floors. Situated in a residential inner city suburb overlooking
a busy main road.
|

|
Three
fifteen story high rise blocks of flats. 41 metres high surrounded by
occupied living accommodation and offices de-construction of the three
blocks were carried out simultaneously. Each block being scaffolded
and covered with fragmentation sheeting to retain all bebris as each
floor was removed. |

 |
Two
twenty two storey high rise blocks of flats, 63 metres high constructed
of 'Camus' purpose built reinforced concrete sectional internal and
external walls and floors. Deconstruction was carried out simultaneously.
Hillsdene overlooked a day are centre within 6 metres and remained in
daily use throughout the duration of the contract, Mountdene also overlooked
a community centre, library and bus stop all within 10 metres of the
structure and were in constant use during deconstruction. |

 |